Gas Power Plant:

Safe design of gas shut-off valves, site survey, process development and design of new plant.

The Problem

Installation of new Slam Off Quick Acting Isolation Valves in a 400mm diameter high pressure gas feed to the turbines. Valves had to be located a minimum distance from the turbine with a dedicated downstream depressurisation vent that could reduce the pressure to 1 barg in less than 15 secs. All equipment had to be accessible for inspection and maintenance.

The Solution

  • Development of a dynamic model to prove hydraulics and depressurisation times are met.

  • Process design package supported by HAZOP to underpin the detailed design work.

  • Pipework routing survey and location assessment for new equipment including groundworks for new platforms.

  • Detailed drawings for piping and structural work supported with stress analysis modelling.

The Benefits

  • “All in one place” engineering service that is supported by cutting edge process, dynamic and mechanical simulation tools.

Services Provided

  • Detailed Site Survey.

  • Dynamic Simulation.

  • HAZOP.

  • Mechanical Piping Design.

  • Stairs & Platform Design.

  • STAAD Pro Structural Analysis.

  • Caesar II Piping Stress Analysis.

  • Constructability Reviews.

  • Gas Dispersion Modelling.

  • IGEM Standards.